Troutbeck — Phased Site Plan Development

Board: Planning Board

Status: Under Review

First Appearance: January 8, 2025

Days Open: 560 days

Location: Troutbeck Resort, Amenia, NY

Project Summary

Troutbeck's phased site plan redevelopment covers 11 planned phases; the Planning Board has approved three site plans to date (Phase 1, Phase 2, and Phase 8). Phase 8 covers reconfiguration of the resort's pool facility, including a new pool layout, a new bathroom building, a new snack shack/amenity building, and conversion of an existing pole barn into an indoor pool facility connected to the barns. Each future phase requires its own separate site plan review and approval.

Timeline

July 22, 2026
Site plan extension approved, 5–0. Board granted a six-month extension of the Phase 8 (pool renovation) site plan approval, moving the building permit deadline from July 8, 2026 to January 8, 2027. The board's attorney confirmed this is the only extension the applicant is entitled to under the original resolution. Full meeting summary →
January 8, 2025
Phase 8 site plan (pool facility reconfiguration) approved by the Planning Board, starting the standard 18-month window to pull a building permit.