Route 44 Sidewalk

Board: Town Board

Status: In Progress

First Appearance: January 2, 2025

Days Open: 567 days

Project Summary

The Route 44 Sidewalk project is a CDBG-funded sidewalk connecting downtown Amenia to Beekman Park. Originally reported as nearly complete in early 2025, the project encountered significant construction issues and has been described as a "debacle" by the supervisor. The CDBG grant expired April 30, 2026, but has been extended with conditions. The town is evaluating proposals from Fountain Square to either repair the existing sidewalk or rebuild from scratch, with approximately $75,000 remaining in grant funds.

Timeline

July 9 & July 23, 2026
The Town Board held executive sessions for advice of counsel on the Route 44 sidewalk project at both July meetings. No public details were disclosed; a board member noted the sidewalk remains a top capital priority ahead of other requests like Mechanic Street retaining wall repairs. July 9 summary → · July 23 summary →
January 2, 2025
Town Board supervisor reported finishing construction of the sidewalk to Beekman Park as a 2024 accomplishment.
December 18, 2025
Supervisor's year-end report noted the sidewalk to Beekman Park was "not quite complete," indicating construction issues had emerged.
March 11, 2026
Sidewalk conditions discussed at Planning Board meeting in context of Cascade Creek site walk along the Route 44 corridor.
April 16, 2026
Town Board discussed lessons learned from the sidewalk project regarding concrete pouring in fall weather conditions. DOT involvement noted.
May 7, 2026
Supervisor reported meeting with Assemblyman Beephan and Senator Hinchey about the "Route 44 sidewalk debacle." CDBG grant for the sidewalk expired April 30th but was extended with stipulations. Approximately $75,000 remaining on the grant. Board received two proposals from Fountain Square for remediation work. Discussion of whether to repair or start from scratch.
June 4, 2026
Pasquale declined the project after his bonding company refused to bond the patchwork repair approach due to liability concerns. The county inspector, DOT (John Walsh), and Pasquale are scheduled to meet on site to determine if the original piecemeal plan can be salvaged; if not, the project would proceed to the third bidder. Grant extension contract signed with monthly progress check-ins required.
June 18, 2026
Full replacement confirmed as the path forward. The aggregate originally used was sourced from the Newia Highway Department and is not DOT-certified, requiring complete removal. Drain issues also identified. Pasquale (KTE) is ready to start within two weeks; estimated cost is $315,000 for a project taking up to three weeks. Bonding company representative Joseph Kaufman (Held) is awaiting a formal quote from Pasquale plus DOT's written justification for full removal before bonding can proceed.