Cascade Creek Subdivision

Board: Planning Board

Status: Under Review

First Appearance: January 8, 2025

Days Open: 609 days

Project Summary

Cascade Creek is a proposed residential subdivision by Hudson River Housing on a 24-acre parcel in the suburban residential zoning district. The project is designed to support workforce housing with uniform four-bedroom houses. As of July 2026, the plan has been reduced from 28 to 26 lots, with a corresponding reduction in overall project acreage. The subdivision includes two HOA/conservation parcels and a new road right-of-way along Cascade Mountain Road.

Timeline

September 9, 2026
Applicant submitted a full preliminary subdivision plat package (plat, grading, stormwater, road profiles, water and septic engineering reports). Town engineer flagged outstanding items — water/sewer transportation corporation structuring, easement widths and detail, county health and state SPDES permitting, road profile details, and identification of a certified third-party conservation organization — but found sufficient information to proceed to public hearing. Board voted to schedule a public hearing for October 28, 2026, in the Town Hall auditorium. Full meeting summary →
August 20, 2026
Hudson River Housing received a $199,000 award to assist with construction of four houses as part of the project's affordable housing component, per the Town Board's supervisor's report. Full meeting summary →
August 26, 2026
Applicant submitted a supplemental application on August 13, updating its July 30 preliminary submission; the update arrived after the agenda deadline, so it will be reviewed alongside the September 9 meeting. The board's attorney and engineer are reviewing the most recent version and do not recommend scheduling a public hearing in advance of that review. Full meeting summary →
July 22, 2026
SEQR negative declaration adopted, 5–0. Applicant returned with a scaled-down plan (26 lots, down from 28, with reduced acreage) and a fire protection plan developed with the Amenia Fire District: individual sprinklers in each home plus two 6,000-gallon domestic water storage tanks. At the request of fire commissioner Peter Dyer, the board's findings specify that no final determination on water storage capacity for firefighting purposes (as opposed to the sprinkler system) has yet been made — that will be addressed during preliminary and final subdivision review. The board also updated its Environmental Assessment Form to address new 2026 DEC questions on climate risk and disadvantaged-community impact, concluding the project — sited in a state-designated disadvantaged community — will have no significant adverse impact. Full meeting summary →
June 10, 2026
SEQR negative declaration fails 4–2. Board voted on the negative declaration; four members voted no (Chairman Robert Boyles Jr., John Stefanopoulos, Ken Topolsky, and Jamie Vitiello) citing fire safety (60,000-gallon water storage vs. fire district's request for 180,000 gallons), density/community character concerns, and desire for mandatory sprinklers. Two members voted yes (Nina Peek, Lyzzette "Foz" Bullock). Applicant (Hudson River Housing, represented by Peter Sander) met with Amenia Fire District the prior evening; fire district still requests 180,000 gallons. Applicant to return at first July meeting with: resolution of fire district water supply dispute, alternative layout addressing density concerns, and sprinkler analysis. A positive declaration was not issued — applicant given opportunity to address concerns and resubmit. Full meeting summary →
May 27, 2026
Revised single entrance to Route 22 presented per DOT request. Updated traffic study submitted — no signal or left-turn lane warranted; crosswalk recommended. Board reviewed SEQR Part Two EAF. Split 3-3 on consistency with community plans. Community character debate over density and housing uniformity. Draft negative declaration distributed for review at next meeting. Fire district meeting recommended regarding 60,000-gallon tank.
January 8, 2025
Initial presentation to Planning Board. Hudson River Housing introduced the 28-lot residential subdivision on a 24-acre parcel in the suburban residential zoning district, designed for workforce housing with uniform four-bedroom houses.
July 9, 2025
Lot line adjustment discussion. Board reviewed lot frontage requirements along Cascade Mountain Road and adjustments needed to provide sufficient frontage for each parcel.
February 25, 2026
Planning Board discussed scheduling a site walk for the Cascade Creek property.
March 11, 2026
School district superintendent Robert Farrier appeared before the Planning Board to address questions about the project's impact on the Webutuck school district. Confirmed the district could accommodate additional students. Site walk conducted.
April 22, 2026
Peter Sander presented updated plans responding to board comments from the site walk. Project includes 28 residential lots, two HOA/conservation parcels, and one road right-of-way.

Documents & Materials

Uploaded Materials

No materials have been uploaded yet.